MIRROR MIRROR The James Webb Space Telescope--an
infrared follow-on to the Hubble Space Telescope--won't
launch until 2013, but Ball Aerospace & Technologies
is accelerating critical work related to focusing the
satellite's huge 18-segment, beryllium primary mirror in
orbit.
Actively controlling JWST's 6.6-meter-dia. (21.6-ft.)
mirror--roughly three times as big as Hubble's--to
tenths-of-nanometer tolerances is a daunting technical
challenge. Although massive, multi-segment mirrors are
used in a number of terrestrial telescopes, such as the
W. M. Keck facility in Hawaii, JWST will be the first
in-space application (AW&ST July 7, 2003, p. 42).
Additionally, the mirror for Webb, named for the
Apollo-era NASA administrator, will require an
unprecedented level of in-orbit control to ensure a
consistently sharp image of deep-space objects.
The program has ballooned to more than $1 billion
over its $3.5-billion budget, prompting NASA to slip the
launch two years. Similar woes beset Hubble in its early
days, and no one wants a repeat of the colossal
embarrassment suffered after it was launched in 1990.
That now-storied observatory had a 2.4-meter,
single-element mirror built and tested by
Perkin-Elmer--but with a test device that had been
improperly assembled. Ball developed a corrective optics
system that was installed during a shuttle servicing
mission in December 1993.
BALL NOW IS ACCELERATING the development of a
one-sixth-scale optical testbed designed to reduce
technical risks associated with controlling the primary
mirror. Those risks must be mitigated prior to a
technical review scheduled for January 2007. To that
end, a full end-to-end "phasing" of the telescope will
be demonstrated via Ball's optical testbed by next
September.
The device was built to validate software algorithms
and sophisticated hardware on the ground, elevating
confidence in the entire optical package prior to launch
of the full-scale telescope. Testbed cost is about $6
million--not counting algorithm development--"a
relatively small, but incredibly important piece" of
Ball's $212-million subcontract, says Mark Bergeland,
Ball's JWST program manager.
"One risk area for JWST is demonstrating an ability
to 'phase' this large, segmented telescope [after] it's
deployed in orbit," he adds. With an onboard camera,
telescope operators "will take images of stars and use
image-based wavefront sensing and control [WFSC] to move
the mirrors into proper alignment.
"When we first deploy the 18 [primary mirror]
segments, they won't be in phase. We'll get 18 different
spots, when looking at a star, as opposed to a nice,
sharp image. We'll go through a series of [WFSC]
processes by first moving the mirrors to identify which
spot corresponds to which mirror [segment]. The next
step is to put . . . those 18 different spots into a
well-patterned array, then bring the 18 into one spot.
They won't be phased, but they'll be coaligned. We then
go through coarse- and fine-phasing [to] align each of
the 18 mirrors and get them all cophased to a fraction
of a wavelength of light."
Each hexagonal mirror segment nominally measures 198
mm. (7.8 in.) across and 10 mm. thick. The testbed
segments are made of glass, but the flight version's are
constructed of very lightweight beryllium. Structurally
strong and thermally stable, beryllium has a coefficient
of expansion close to zero at 40 Kelvin, where the JWST
will operate. Each flight segment also is being
manufactured to "92% light-weighting," Bergeland says. A
blank of beryllium material starts at about 540 lb., but
is machined to a mirror segment weighing about 46 lb.
However, controlling movements of either the glass or
beryllium segments involve the same mechanics. "Each of
the [mirror] segments--on both the flight [model] and
the testbed--has seven actuators on the back," he
explains. "Six control rigid-body motion in six degrees
of freedom, and the seventh actuator controls the
segment's radius of curvature," which is required to
focus the mirror.
In a fine-phasing process, these actuators can
control movement "to a nominal step size on the order of
8-10 nanometers. That's the kind of resolution we need
to phase the full telescope," he notes.
A number of tests over the next 6-9 months will
ensure WFSC algorithms developed by Ball and
subcontractor Adaptive Optics Associates are mature
enough to function properly in orbit. All the algorithms
will be "exhaustively tested on the one-sixth-scale
telescope testbed," says Duncan Shields, Ball
Aerospace's wavefront sensing and control manager.
Sensing a light wavefront is accomplished through a
complex process known as "focus-diverse phase
retrieval." That means, "when the [light] points are
stacked, and all the mirror [segments] are fairly close
to the right [position], we put a series of defocus
lenses in the beam and look at how that perturbs the
wavefront," Shields explains. "In so doing, we can
extract exactly what final corrections need to be made
in tilt, tip . . . and so forth to make the best
possible wavefront [through] fine-phasing over a wide
field of view."
Still, the system is designed to enable rephasing
about every 30 days in orbit, tweaking the wavefront
periodically to ensure a sharp image.
Ball engineers' primary long-term concern is
"understanding and maintaining the stability of the
telescope" in space. Because the JWST will be positioned
at the L2 Lagrangian point, about 930,000 mi. from
Earth, it will be subjected to cryogenic temperatures
throughout its 5-10-year mission.
"The telescope will nominally operate at about 40
[Kelvin]," Bergeland says. "Just pointing to different
portions of the sky will change its temperature
slightly, and at the level of nanometer resolution,
that's a significant concern. [The structure] has to be
thermally stable enough to maintain the telescope's
phasing. This is a passively cooled telescope, and any
heat that gets from the spacecraft to the mirrors
potentially can cause deformations" that will distort
images. "Because our tolerances are tenths of
nanometers, that really gives [our] mechanical engineers
headaches," Shields adds.
DESPITE THE THOROUGH testing now planned, Ball's
mirror-control system will ensure unanticipated in-orbit
problems can be corrected. Every engineer and manager
working on JWST recalls Hubble's initial fuzzy images,
and measures are being taken to avoid that nightmare.
"We've incorporated design [measures] to give us the
flexibility to [correct errors]," Bergeland says. "For
instance, the six actuators in the system give us full
six-degrees-of-freedom motion. That's more than we
believe we'll really need, but it gives us a backup
capability to [adjust mirror segments] in six degrees of
motion rather than three. By design, we've incorporated
the capability to fix issues if we run into [problems]
on orbit." |